Weekly Road Construction Report

Thursday, August 10, 2017

Here is the weekly road construction report for Hamilton County: 

I-24 East bridge repair over Chestnut Street at mile marker 178.6 near the U.S. 27 interchange and safety improvements on the bridges over the CSX Railroad and over U.S. 27:  Work will begin this week on a project to repair the bridge on I 24 East over Chestnut Street at mile marker 178.6 near the U.S. 27 interchange.  The project will also make safety improvements on two other bridges in the same area, one over the CSX Railroad and one over U.S. 27.  In addition to making major bridge deck repairs to the bridge over Chestnut Street, this project includes the installation of high-friction surface treatment on all of the bridge decks.  On Thursday and Friday nights, between 7 p.m.-6 a.m. EDT, the contractor will begin shifting traffic and reworking overhead signs.  Once the traffic is shifted and the signs reworked, work on the project will begin.  If rain postpones this work, it will be rescheduled to take place as soon as possible.  During the project, the bridge on I-24 East will be completely closed to traffic and a detour using the Lookout Mountain/Broad Street ramp (Exit 178) will be used to move traffic around the work zone and allow it to continue on I-24 East.  Once I-24 East is closed for bridge repairs, all repair operations will be done using a continuous daily operation (seven days per week) until necessary repairs are completed and/or all lanes are open to the free, unrestricted flow of traffic.  Additionally, traffic accessing Lookout Mountain/Broad Street from U.S. 27 South will be detoured until completion of the project.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is November.  [Dement Construction Co., LLC/Pruett/CNR031] 

U.S. 27 (I-124) widening from I-24/U.S. 27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge:  Work on this project continues.  The speed limit on U.S. 27 in the construction zone is 45 MPH.  On weeknights during this report period between 7 p.m.-6 a.m., the contractor will have a temporary left lane closure on U.S. 27 South from Manufacturers Road to I-24 for beam removal.  Southbound Exit 1A will be closed during this time due to Eastbound Martin Luther King Boulevard being closed.  On U.S. 27 South, traffic has been shifted to the right on U.S. 27 South from 4th Street to MLK Boulevard to allow the contractor to safely work in the middle portion of the road.  Traffic is impacted by the loss of acceleration/merge areas onto U.S. 27 South from the on ramps at 4th Street and MLK Boulevard.  On U.S. 27 North, traffic has been shifted to the right on U.S. 27 North from I-24 to MLK Boulevard to allow the contractor to safely work in the middle portion of the road.  Traffic is impacted by the loss of acceleration/merge areas onto U.S. 27 North from the on ramp at MLK Boulevard.  The new loop ramp from eastbound MLK Blvd. to U.S. 27 North is open and the previous left turn to the northbound ramp is closed.  Ramp traffic must yield at these locations.  The contractor may have temporary lane or shoulder closures on U.S. 27 between 7 p.m.-6 a.m.  At least one lane will remain open in each direction on U.S. 27.  THP will assist with traffic control on the project as necessary.  Estimated project completion date is July 2019.  For more info, visit the project website http://www.tn.gov/tdot/topic/US27-reconstruction-chattanooga.  [Dement Construction Co., LLC/JM/CNP230] 

SR 317 (Apison Pike) the grading, drainage and paving on from Old Lee Highway (LM 5.58) to SR-321 (Ooltewah-Ringgold Road) (LM 7.84):  Work on this project continues.  During this report period the contractor may have intermittent lane closures throughout the project from 9 a.m.-4 p.m.   Flaggers will assist with traffic control as needed.  Estimated project completion date is August. [Wright Brothers Const. Co. /Pruett/CNN279] 

SR-320 (East Brainerd Road) grading, drainage, installation of signals, construction of seven retaining walls and paving from east of Graysville Road to east of Bel-Air Road:  Work on this project continues.  During this report period, the contractor will have intermittent lane closures between 9 a.m.-2 p.m.  This work may affect either direction of East Brainerd Road or side streets from Graysville Road to Hamlett Drive as the contractor installs road crossings and borings.  Traffic has been switched onto the newly-constructed section from the west end of the project to the Hurricane Creek Road/East Brainerd Road intersection, allowing the contractor to work on the other side of the roadway.  The contractor may have short-term lane closures to perform various operations on an as-needed basis.  Flaggers will assist with traffic control as needed.  Estimated project completion date is June 2018. [Jones Brothers Contractors, LLC /Pruett/CNN383] 

SR-153/SR-319 (Hixson Pike) bridge repair on Hixson Pike over SR-153:  Work on this project continues.  The contractor will be working on the inside lanes of the bridge.  The outside lanes in both directions are open to traffic.  This lane closure will be in place until late November.  During this report period the contractor may have intermittent lane closures on SR-153 from 9 p.m.-6 a.m. to do work under the bridge.  If there are any temporary closures needed on SR-153 as part of this project, they will take place at nighttime on Sundays through Thursdays between 9 p.m.-6 a.m. and on weekdays on SR-153 South between 9 a.m.-3 p.m. and on SR-153 North between 7:30 a.m.-3 p.m.  Flaggers will assist with traffic control as necessary during these temporary closures.  Estimated project completion date is May 2018. [Mid-State Construction Co. /Micka/CNQ941] 

U.S. 27 (SR-29) resurfacing from north of Signal Mountain Road (LM. 3.02) to north of SR-29 (MM. 6.0/LM 6.07):  This project is complete.  There are a few minor punch list items to be corrected.  However, no lane closures will be required.  Contractor has been authorized to remove all signs.  Estimated project completion date is August. [Wright Brothers Construction Co, Inc./Micka/CNQ189] 

SR-153 resurfacing from L.M. 7.11 (Chickamauga Dam) to LM 8.89 (Hixson Pike):  Work on this project continues.  Milling operation will require lane closures from 9 p.m.-6 a.m.   Lane closures are limited to Sunday night thru Thursday night from 9 p.m.-6 a.m.  Estimated project completion date is September.  [Wright Brothers Construction Co, Inc./Micka/CNR133]

The tunnel cleaning of the McCallie Tunnel on U.S. 11 (US 64, SR-2), the Stringers Ridge Tunnel on U.S. 127 (SR-8), and the Bachman Tubes on U.S. 41 (U.S. 76, SR-8):  The nighttime cleaning operation of McCallie Tunnels, Stringers Ridge Tunnel, and Bachman Tubes occurs between 8 p.m.-6 a.m.  Tunnels will be closed during cleaning, and detours will be marked accordingly as each tunnel is cleaned.  Contract completion date is June 2018.  [ETI Environmental, Inc./Micka/CNR223]




West Village To Host Family-Friendly New Year's Eve Festival

Families are invited to a New Year’s Eve festival in Chattanooga’s newly-revitalized West Village area between MLK and 7th on Chestnut and Pine near the base of the just-opened Westin Hotel. Lights are twinkling and the spirit of the street is changing as the West Village brings a European-style experience to Chattanooga families, said officials. Beginning at 6 p.m. on Sunday, ... (click for more)

McKamey Animal Center To Hold 12-Hour Adoption Event On Friday

Home for the Holidays or Bust! That is the mantra of the staff and volunteers of local animal shelter McKamey Animal Center in Chattanooga. Volunteers and staff members are gearing up to help as many animals as possible find a home for the holidays. Shelter staff and volunteers will be staying for a "Holiday All-Nighter" at the shelter on  Friday, from noon until midnight ... (click for more)

1 Killed, Another Injured In Shooting On The Southside Early Sunday Morning; Delivery Driver Carjacked On Southside Earlier

One person was killed and a second person injured in a shooting on the Southside early Sunday morning. The victims are Sharone Porter, 22, who was killed, and Torrie Porter, 24, who had non-life threatening injuries.  At 2:47 a.m., Chattanooga Police responded to 1400 Cowart St.  on a person shot. Upon arrival, Chattanooga Police found two victims suffering ... (click for more)

Bradley County Deputy Shoots And Kills Stabbing Suspect At Charleston

A Bradley County deputy shot and killed a man who was a suspect in a stabbing early Sunday morning. The Sheriff's Office said, "At approximately 11:54 p.m. on Saturday, a call was received at the Cleveland/Bradley County 911 Center to report a stabbing at a residence on Leyland Drive in Charleston. "The caller indicated a male had been stabbed and another male had fled from ... (click for more)

The Growing Monopoly

Over the last decade, five tech giants have risen to the top, and created, discovered and invented services and products that have made these companies worth billions today. Those five, of course, are Facebook, Apple, Amazon, Microsoft, and Google. Each of these companies are responsible for several products and services that we use in our everyday lives. They have devoured the ... (click for more)

Roy Exum: The Last Day Of School

AUTHOR’S NOTE: This story first appeared in the Chattanooga News-Free Press in the late 1970s and every year about this time I am asked repeatedly about it. It is far and away the most famous story I have ever written – copies have been sent to me from numerous foreign countries, it’s included in teaching manuals and people I haven’t seen in years get in touch when they read it ... (click for more)